Dalekovod d.d. has received a Notification on the Ceremonious Ceremony of Signing the Contract on Construction of Ernestinovo-Pecs 2x400 kV Transmission Line, Section Ernestinovo – State Border
(09/10/2007)
Construction of Ernestinovo-Pecs 2x400 kV Transmission Line, Section Ernestinovo – State Border is of strategic importance for realization of infrastructural prerequisites for safe power supply of the areas of Slavonia and Baranja. Besides, the project is of highest international importance as it is runs along the priority international electric power course North-South.
The contract shall be signed by companies HEP Operator prijenosnog sustava d.o.o. and Dalekovod d.d. Zagreb on 14 Nov 2007 in Osijek.
The contract is valued at ca 159 million kunas and the anticipated completion date is 1 Dec 2009.